MORGANTOWN - The Public Service Commission has given Mon Power and Potomac Edison the OK to build a 1,200-megawatt combined-cycle natural gas power plant at its Fort Martin site in Maidsville, along the Monongahela River.

The Tuesday PSC order also OKs the companies’ plan to build an additional 70 MW of solar capacity.

The gas-fired plant, called the Maidsville Energy Center is estimated to cost $2.48 billion. The three solar sites - at Valley Point near Albright, W.Va.; Davis, adjacent to the West Virginia town with the same name; and Wylie Ridge near Weirton, W.Va. - will cost $182 million.

The PSC also approved the companies’ requested Generation Projects Surcharge to recover financing costs incurred during construction and after the facilities enter service, until those costs are included in base rates. The companies estimate that the initial surcharge will result in a rate increase for residential customers of $1.18 per month or 0.9%.

The PSC order notes that the companies also requested approval of a transmission project interconnect of less than one mile, with an anticipated cost of over $20 million. Mon Power applied to PJM Interconnection for an interconnection agreement on April 24. The expected PJM processing time is one to two years.

The Maidsville Energy Center will be the first major power plant in Monongalia County since 2011, and FirstEnergy’s first plant since 1972.

The companies initially filed their application in February, citing the need for additional electric generation capacity due to a projected shortage beginning in 2029 and continuing through 2045.

The plant will be considerably smaller than its coal-fired neighbor. FirstEnergy told The Dominion Post in May that it will not have the tall stacks and cooling towers like its coal-fired neighbor. The Energy Center’s cooling towers will be a 12-cell rectangle of low-slung mechanical-based units with mechanical fans on stands.

A combined cycle plant uses both gas and steam combustion turbines to generate electricity. In the gas combustion turbine, air is pressurized using a compressor, injected with fuel and ignited to generate high-temperature pressurized gas that expands to drive the turbine and generate electricity. The waste heat from the gas turbine is then used to generate steam to drive a steam combustion turbine for additional electricity generation.

The PSC directed the companies to provide updates on construction progress and costs as part of their annual filings in January 2027. The companies also must notify the PSC at least 30 days before construction begins.

FirstEnergy told The Dominion Post in May that is estimating 2,000 construction jobs. It will be all union trade labor - except for possibly a couple highly specialized contracts - and all from the area.

They project the total cost for the plant to be $2.476 billion, beginning this year and running through 2033. It will produce and estimated $500 million in local and state taxes. The plant itself will employ about 25 people.

The Maidsville Energy Center is projected to go online in 2031.